Estimate the quantity of soil to be excavated from the borrow pit​

Respuesta :

lola2487
lola2487 lola2487
  • 04-08-2019

Answer

1056

Explanation:

for example

A soil is to be excavated from a borrow pit which has a density of 1.75g/cc and water content of 12%. The G is 2.7 the soil is compacted to that water content of 18% and dry density of 1.65g/cc. for 1000 m3 of soil used in fill estimate

Quantity of soil to be excavated from pit in m3

Answer Link

Otras preguntas

what do you think the blue danube is about?
9. When Margot applies for a loan, she needs to demonstrate to the bank that she has capital. What could she show them to best demonstrate her capital? -copies
The Kinetic energy of molecules of a gas increases with​
SMART PEOPLE PLEASE HELP!! This is timed and super important! No fake answers, I will report links. I'll give brainiest to correct answers.
The Answer please!!!
Which of the six simple machines does this tool have?
Which of the following statements illustrates the standard of living as measured by the Gross Domestic Product? A. The Smiths can buy everything they want and n
Hii! Does anyone know the answer to this? I’m bad at geometry and need help! Thank you
HELP ME ASAP PLSSSSSSSSS
how can i get the answer to 5(2x -3) by using distributive property??.. pls help im stuck