A can do a piece of work in 20 days and B can do it in 12 days,B work for 9 days,in how many days A alone can do the work​

Respuesta :

roseheart889 roseheart889
  • 03-09-2020

Answer: 9

Step-by-step explanation:

Answer Link

Otras preguntas

HELP I NEED THE ANSWER FAST ILL MAKE U BRAINIEST!!!!!!!!! NASA was created as a direct response to the competition of the Cold War, trying to establish American
(2) Why do spring balance shows wrong reading after they had been uses for a long time?​
ways of improving sanitation in the school​
worth 10pts can someone help?
okay so basically i need to make a video on how technology is a two edged sword and i need to show its negative and positives? but i’d like for ideas as i can’t
Where is DNA found in the cell??????
Identify the triangle, ABC, which has a 72∘ angle and a 36∘ angle.
Choose 3: Which of the following did Frederick the Great implement during his time as the first servant of the state Treform Prussia? Select one or more: a. Red
Your help will really be great plz help me
What is it that has eyes but does not see?answer with intelligence.​