In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Tim has developed a money saving strategy that uses the formula S=450+100r. a. Give a possible interpretation of Tim's strategy. b. What do the slope and S-inte
In the word solitaire, the root sol- mean a. Man b. Alone c. Sun d. Person
Who rescues the narrator from his prison, on the story "The Pit and the Pendulum?
1. Why was the government of ancient Athens called a direct democracy?
how do you say Avery in spanish.
which of the following is a viewpoint espoused by Locke?a)the idea that government was instated to preserve life, liberty, and property.b)the idea that governme
I am a force canceled out by other forces on the same object what am i
In the word solitaire, the root sol- mean a. Man b. Alone c. Sun d. Person
A SPORTING GOODS COMPANY CAN SHIP 6 FOOTBALLS IN EACH CARTON. HOW MANY CARTONS ARE NEEDED TO SHIP 75 FOOTBALLS
Which of the following vocabulary words ends in a suffix that indicates it is an adjective a.imminent b.doggedness c.infallibility